FRC 2009 Design Build Test Schedule

    Week 1 (1/10/09)   Week 2 (1/17/09)   Week 3 (1/24/09)   Week 4 (1/31/09)   Week 5 (2/7/09)   Week 6 (2/14/09)  
Task M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
Place Order: Sm. Parts & Add. Hardware C                                                                                  
Brainstorm on all possible Robots/Tactics X X C                                                                              
Proto Half Scale Robots       X X X X X X X X X C                                                          
Field Construction         X X X X X X X X X X X X X X X X                                            
Decide on Robot Concept X X X X X X C              
Electrical - Power & Control System                                                                                    
  Concept Design                         X X X X X X X X                                            
  Fab prototype                                                                                    
  Fab Final System                                                                                    
Programming - Autonomous Mode                                                                                    
  Concept Design                                       X                                            
  Fab prototype                                       X                                            
  Fab Final System                                                                                    
Programming - Drive & Scoring System                                                                                    
  Concept Design               X X X X X X X X X X X X X                                            
  Fab prototype                   X X X X X X X X X X X                                            
  Fab Final System                                                                                    
Mechanical - Drive Train                                                                                    
  Concept Design               X X X X X X X X X X X X X                                            
  Fab Crude Proto to test power/speed                                                                                    
  Fab Final Drive                                                                                    
Mechanical - Chassis                                                                                    
  Concept Design                   X X X C                                                          
  CAD modeling of all systems                         X X X X X X X X                                            
  Fab Chassis                         X X X X X X X X                                            
Mechanical - Integrate Drive/Chassis                
Scoring System                                                                                    
  Concept Design               X X X X X C                                                          
  Fab prototype                                                                                    
  Fab Final System                                                                                    
Integrate proto systems as needed                                                                                    
Integrate Final Systems                                                                                    
Test & Drive & Upgrade & Test & Test                                                                                    
Prepare shipping crates C                                                                                  
Ship Robot                                                                                    
X = Progress C = Completed Good Caution Behind Schedule Task Start/Stop